Planning a sprint in JIRA Agile involves assigning issues. You want to spread the load fairly, not overburdening or underburdening workers. To complicate matters, some issues take longer than others (with more Story Points or greater Time Estimate), and the capacity of each worker varies per week, as they may have time off or other responsibilities.

To meet this planning need in a simple way, we have developed the Sprint Capacity Report, a Confluence-based SQL report showing issues grouped per assignee, showing time estimates vs. assignee capacity

:

.

 

 

The sprint to show is selected in a drop-down. Here we can see, for instance, that Dave is able to work 10 hours this sprint, is assigned one issue (SKP-14), which is estimated to take 30h, so Dave would be at 300% capacity unless we change things.

...